1, the location of the unit should be avoided as much as possible close to the fire source and flammable materials. If you have to set up with the boiler and other heat generators, we must fully consider the impact of heat radiation.
2, the refrigeration unit placed in the ambient temperature should not exceed 45 ° C and well ventilated place. Installation location should not exist corrosive gases; 3, the refrigeration unit should be selected.
3, the refrigeration unit should be selected in the dust, leaves and other impurities less place; 4, the refrigeration unit as far as possible in the place of the refrigeration unit.
4, the refrigeration unit as far as possible placed in the place of good lighting, so as to facilitate the maintenance and inspection.
5, in order to facilitate the lifting of the refrigeration unit and maintenance and other installation operations, it is necessary to set aside space for the installation and maintenance of the unit.
6, the refrigeration unit should be placed in a relatively high position, there is no water in the place; screw chiller installation foundation construction requirements
Screw refrigeration compressor running parts are relatively small, so its stability is relatively high, so it is for the foundation of the dynamic load to be smaller. In order to prevent corrosion of the refrigeration unit foot parts, the drainage around it must be good 1 machine base steel plate corresponding to the foundation plane should be as smooth and flat as possible. Specific requirements are.
1, the height difference between the various foundation surfaces should not exceed 3mm; in order to facilitate the maintenance and inspection of the refrigeration unit’s height should be greater than 100mm, and around the arrangement of drainage ditches;.
2, there should be no gap between the steel plate of the base and the foot plate of the refrigeration unit body. Between the two should remember to add anti-vibration rubber pads, the base of the steel plate should be kept horizontal, the height difference should be controlled within 0.5mm. The ground foundation must be cement or steel structure.
Post time: Dec-15-2023